Town of Schererville
Town of

Schererville

US 30 Roadwork - November 2017

 

INDOT US 30 Roadwork updates:

US 30 Underpass near Walmart/Walgreens -

 

Installation of asphalt surface at the RR viaduct between the Applebee’s light and the Joliet Street light.
11/9 – Paving will begin in the passing lanes, both directions, moving into the drive lanes as time allows.
11/10 – Finish paving the drive lanes if needed then move onto the shoulders, both directions.

Grading work to restore positive drainage in the median(s) on both sides of the viaduct will be scheduled after the surface paving work is completed. This will include concrete pads that will slope down to the median inlets around the guard rail posts in both east & west bound lanes.

_____________________________

Lane restrictions between Austin & Cline Avenues and Pine Island Drive & Whitcomb Street - Work expected to continue at a minimum of 10 more working days.

US 30 will be restricted down to 1-lane in each direction as follows:

Micro-surface milling/leveling of the concrete roadway sections at the Bike Trail Overpasses.
11/8-11/9 – Erie Trail/Pine Island Drive overpass passing lanes both directions.
11/10-11/11 – Erie Trail/Pine Island Drive overpass drive lanes both directions.
11/13-11/14 – Pennsy Trail/Cline Avenue overpass passing lanes both directions.
11/15-11/16 – Pennsy Trail/Cline Avenue overpass drive lanes both directions.

For more information on these projects, check back on our social media pages for updates or contact the Indiana Department of Transportation LaPorte District.

Back to news

Phone: 219-322-2211

© Copyright 2024, Town of Schererville. All Rights Reserved.